- After the status is set to Completed, its activities cannot be deleted.
- The Completed status cannot be selected manually if the deliverable has a workflow. The deliverable can only be completed by going through the workflow and completing the last step.
- When the Completed status is selected for an online deliverable, working copies open in read-only mode. To make the document editable again, the owner must change the status to In Progress.
- Changing the status to Completed also changes the Percent Complete value for the document to 100% in Microsoft Project.
- Deliverables status should not be changed to Completed until all predecessors are completed.