• After the status is set to Completed, its activities cannot be deleted.
  • The Completed status cannot be selected manually if the deliverable has a workflow. The deliverable can only be completed by going through the workflow and completing the last step.
  • When the Completed status is selected for an online deliverable, working copies open in read-only mode. To make the document editable again, the owner must change the status to In Progress.
  • Changing the status to Completed also changes the Percent Complete value for the document to 100% in Microsoft Project.
  • Deliverables status should not be changed to Completed until all predecessors are completed.