Automatically Adding Team Members as Project Resources
Accolade's Resource Planning component allows Project Managers the ability to automatically list team members, that have already been added to a project, as resources.
To enable the setting to add team as resources:
- From the System menu, select Process > All Models, then select a model.
- In the Process Definition tab, locate the section Team Project Rights, and click on the Add Team as Resources check-box. By default, this setting is off.
- Click on Apply.
To add team members as resources:
- Display a project, and select the Team tab.
- Select the check-box corresponding to the team members you wish to automatically add as project resources.
- Click on Add Team as Resources.
Note: Only team members that are part of a resource pool can be added as project resources.
Your team members have been successfully added as assigned resources to your project.
Notes:
|
Learn More:
- Allocating Assigned Resources to Resource Demand Requests
- Approving Resource Plans
- Automatically Adding Team Members as Project Resources
- Plan Projects (Beta) Page
- Requesting Resources Using Deliverables and Activities
- Resource Editor at a Glance
- Resource Editor Net Capacity Resource Calculations
- Transferring Demand to Other Resources
- Viewing Resource Capacity & Managing Resource Attributes
- Viewing Resource Plans