Allocating Assigned Resources to Resource Demand Requests

Resource Planners can allocate assigned resource demands with requested demands to show that they intended to satisfy or allocate request for a resource with a specific resource assigned to a project demand. This association provides visibility into what has been allocated to satisfy a requested demand.

Important! If you use Accolade Portfolio Optimizer to manage your resource demands and commit demand information back to Accolade, any allocations between requested and assigned demands are removed when you commit a scenario to Accolade.

Resource Planners can do the following:

In addition, Resource Planners can edit the demands that are assigned to a document owner. These demands display as Assigned, and are either assigned to the owner, or to a system-generated resource based on the deliverable or activity function if an owner is not set. Click Note Icon in the demand row to see which deliverable or activity is associated with the demand. Resource Planners can update these demands as necessary.

Assigning Resources Within a Project

Resource Planners can also assign resources for a project from within the project Resources page. Users with access to the project can also use the Resources page to review the resource requests, and those resources currently assigned to the project. Resources requested through the project pages are also available for review and modification within Resource Editor.

To assign a resource from within a project:

  1. Display a project and select the Resources Resource Page Icon page.
  2. Do one of the following:
  • To view a resource for a project stage - In the Plan For field, select the specific stage.
  • To view a resource for the entire project - In the Plan For field, select Project.

Pools with existing requested or assigned resources display. Click Expand Icon to expand the display and view the requested or assigned resources.

On the project's Resources page, click the Green Check Icon or Partial Icon icon next to a pool name to view the demand history of the resources in that pool. Green Check Icon indicates that the Project Manager made the most recent change to requests for the pool. Partial Icon indicates that a Resource Planner made the last change in the pool.

  1. Do one of the following to assign a resource to meet the Project Manager's resource request:
Request Type Instructions

Assign the requested resource to the stage or project

In the Demand Type field for the resource demand request, select Assigned.

Add a resource to the stage or project to meet the demand request

Review the Project Manager's requests in the Resource Plan section of the screen. To assign a resource to the stage or project, add a resource from a resource pool that you own, or that does not have an owner.

  1. In the Pool field, select the resource pool that contains the resource to assign.
  2. In the Resource Availability section, select the check box next to the resource you want to assign.

The Resource Availability section displays the resources within the pool, and the availability for each time period. If a resource displays a negative availability number, that resource is over allocated for that time period.

  1. Click Add to Resource Plan.
  2. In the Demand Type field for the resource demand request, select Assigned.

You can assign a partial resource, such as 0.50 full time employees (FTE).

  1. Click Apply to save your changes.

Assigning Resources Using Resource Editor

Resource Planners can assign resources from pools that they manage using the Resource Editor, which provides a means to assign resources for more than one project at a time. Resource Editor displays all demands with resources that belong to a pool that is related to at least one of the assigned pools that you own.

Note:  Using Resource Editor is the recommended method for assigning demands to multiple projects at a time. However, Resource Planners can also review and assign demand using the Planning page available from the Resources menu.

To assign resources to one or more projects using Resource Editor:

  1. From the Resource menu, select Resource Editor.

  2. Display projects or demands and apply filters as necessary.

Requests display shaded in blue. Use the Expand Icon or Collapse Icon options to expand or collapse a row or grouping. To expand or collapse all rows or groups displayed, use the Expand All Icon and Collapse All Icon option in the table header.

In Resource Editor, the Green Check Icon or Partial Icon icon next to the resource indicates the fulfillment status for the resource. Green Check Icon indicates that the demand request is fulfilled. Partial Icon indicates that the demand request is not or is only partially fulfilled.

  1. Click Resource Add Icon next to the requested demand to which you want to allocate an assigned demand.

The list of available resources is automatically filtered to just those belonging to pools that are related to the pool that contains the resource in the requested demand. If you own no resources in related pools the list contains all resources that you own.

  1. From the resources list, select the resource you want to assign and click OK.
  2. Assigned demands must have the same unit of measure defined in their resource pool as the requested demands they are fulfilling.

    The assignment displays grouped with the request and displays in bold with New Resource Demand Icon to indicate it is a new demand with no demand values assigned.

  3. (Optional) Click Show Rows Icon and select Net Allocation in the upper right of the Resource Editor page to display the Net Allocation row for the requested demand.
  4. Requested demands that have not been fulfilled by allocated assigned demands display in red.

     

As you make edits in Resource Editor, Changed Resource Demand Icon next to a demand row indicates an edit to an existing row that has not been saved.

To enter comments about the allocations you have made, click Note Icon in the row and enter any information regarding your requests or modifications. Note that if Portfolio Optimizer is used to manage resources, comments are removed when resources are committed from Portfolio Optimizer back to Accolade.

  1. Click Apply to save your changes.

Notes:   

  • To delete an assigned resource in the project Resource page, select the line in the Resource Plan section and click Delete Entry.
  • To delete an assigned demand in Resource Editor, click Grey Delete Icon next to the requested resource under a project. The row is shaded to indicate it is pending deletion and is removed when you click Apply. Deleting a demand row deletes all demand assigned within that row, even if it is not visible in the displayed time period. Click Undo Icon to undo the deletion prior to applying changes.
  • To change an assigned demand in Resource Editor, delete the assigned demand and create a new association.
  • When a project becomes inactive (through Close, Hold, or Kill actions), resources for the current and previous time periods will display as read-only on the project's Resources page, and future requested and assigned demands will not display on any resource page. If a project becomes active again, the requested and assigned demand values will display from the current time period forward.

  • When a user is deleted from Accolade, the user is also removed from any resource plans unless the user has active demands on their time. If you delete or transfer all active demands, the user will disappear from the resource plan and can then be deleted from the resource pool.
  • If the Enable Extended Demand Constraints system parameter is enabled, see Defining Resource Editor Filters.
  • Resource Planning is an optional Accolade component that you may not have access to. To implement this solution, contact Sopheon Customer Support .