Assigning Document Owners

Ownership of project documents determines a team member's rights to upload and publish new versions. Ownership of a deliverable or activity can be either explicit (an owner is specifically assigned) or implicit (ownership is inherited when an explicit owner is not assigned) and can be assigned in the following ways:

To view a list of all the assignments for a team member in a project, click the Team Team Page Icon page. Click Team Member Details Icon next to the team member's name to view their assignment, gatekeeper, and workflow action details.

To manually assign an owner to a project document:

  1. Display the project in which you want to assign a document owner.
  2. Click the Stage in the model graphic to display the project stage that contains the deliverable.

If you are assigning an owner to an activity, expand the deliverable to display its activities.

  1. In the Owner column for the deliverable or activity, select a member of the project team.

Depending on how the deliverable or activity is configured in the model, ownership of a deliverable or activity may be restricted to users with a specific user role or to users assigned the function set for the deliverable or activity.

  1. Click Apply to save your changes.

You can also set a deliverable or activity owner from the deliverable or activity details.

Collaborative Document Ownership

If the document is set as collaborative, team members can assign and unassign themselves as the owner. This allows different team members to work on the same deliverable or activity in turn. The Allow Team Members to Share Assignments system parameter enables and disables collaborative documents. The availability of the Allow shared ownership check box within the Deliverable/Activity Details is dependent on the deliverable and activity display configuration. See Defining Deliverable and Activity Details Display Options.

You can assign owners to a collaborative deliverable just as with non-collaborative deliverables. The difference is that owners can unassign themselves and allow other team members to become the owner.

To enable collaboration on a document:

  1. Display the project in which you want to assign a document owner.
  2. Click Stage in the model graphic to display the project stage that contains the deliverable.

If you are assigning an owner to an activity, expand the deliverable to display its activities.

  1. Click the deliverable or activity name that you want to make collaborative.
  2. In the Contents tree, click More Details to display additional details about the deliverable or activity.
  3. Select the Allow shared ownership check box.
  4. Click Apply to save your changes.

Notes:   

  • If a document contains a report created with Accolade Office Extensions, do not assign a Restricted Team Member as the owner. That user role does not have rights to refresh this kind of report in the document.
  • If a user is deleted or deactivated in Accolade, they are removed from the project team; however, they remain listed as the owner of any the documents in the project. To reassign ownership of their document assignments, see Assigning Document Owners. For reporting and record keeping purposes, deleted or deactivated users remain as the recorded owner for documents that have a Completed status.