Modifying Gate Dates in Gantt Planning Views

If an element is based on a gated class, Process Managers with Manage Process rights, or an element's assigned Team Leader, can update the element's gate dates directly from the Gantt view.

Note:  The Allow Project Owner to Set Gate Dates parameter must also be set to 1 for an assigned Team Leader to be able to modify the element's gate dates.

To modify an element's gate dates in a Gantt view:

  1. From the Planning menu, select Planning Board.
  1. Create a view or display a saved Gantt view.
  2. Hover over the element and click Menu Icon to open the element for editing.
  3. In the Details tab, click each gate date field and select the new gate date.
  4. Click Done to apply your changes.

Notes:   

  • If the Gantt view displays project gate dates in the view, hovering over an element's gate icons will display the project name, gate name, and the date.
  • The Gantt view is part of Accolade Roadmapping, an optional Accolade component that you may not have access to. To implement this solution, contact Sopheon Customer Support.